May 24, 2019 – Launch of works for the New Galeazzi Hospital | Milan Ingegneria

On May 24, the construction of the New Galeazzi Hospital began with the completion of a sizable foundation area, measuring 190 meters long, 50 wide and 3.5 meters deep. 33.000 cubic meters of concrete will be laid without interruption in 120 continuous hours.
The Galeazzi Hospital is part of the MIND (Milano Innovation District) to be built in the existing Milan EXPO 2015 area in Rho: a place where work, research, services, living and leisure can coexist, giving birth to the Milan of the future.